VANCOUVER, BC / ACCESS Newswire / October 14, 2025 / Avino Silver & Gold Mines Ltd. (TSX:ASM)(NYSE American:ASM)(FSE:GV6) a long-standing silver producer in Mexico , reports production has remained strong during the quarter, with 580,780 silver equivalent ounces, reflecting steady operational performance, although slightly lower than the previous quarter due to normal mine sequencing. Overall results continue to support the Company's original production estimate of 2.5 to 2.8 million silver equivalent ounces.

PRODUCTION HIGHLIGHTS - Q3 2025 (COMPARED TO Q3 2024)

  • Silver Equivalent Production Decreased 13%: Avino produced 580,780 silver equivalent ounces in Q3 2025, representing a decrease from Q3 of 2024. The decrease was driven by lower feed grades in all three metals (silver, gold and copper), as we moved through a lower grade section of the mine plan and was partially offset by significantly improved mill availability of 21%.

  • Continued Elevated Mill Throughput: In Q3 2025, Avino achieved 21% higher mill throughput versus Q3 2024, totalling 188,757 tonnes of material. These throughput levels built of last quarter's record and were a result of previous upgrades and automation enhancements made by our operations team, demonstrating significant improvements in mill availability.

  • Gold Production Increased 19%: Q3 2025 production of 1,935 gold ounces represented a 19% increase compared to Q3 2024. This improved production resulted from the increased tonnes processed, alongside significant improvements in gold recoveries to 74% from 69% in Q3 of 2024.

  • Silver and Copper Production Decreased 7% and 26%: Avino produced 263,231 silver ounces and 1.3 million pounds of copper in Q3 2025, a decrease in both metals from Q3 of 2024. This decrease was result of lower feed grade from certain areas in our planned mine sequencing, which did have an impact on recoveries as well. This was partially offset by significantly improved mill availability of 21%.

Avino Mine Production Results

Q3
2025

Q3
2024

Change

YTD
2025

YTD
2024

Change

188,757

156,512

21%

Total Mill Feed (dry tonnes)

547,597

467,041

17%

52

63

-18%

Feed Grade Silver (g/t)

54

63

-14%

0.43

0.46

-6%

Feed Grade Gold (g/t)

0.45

0.47

-4%

0.39

0.58

-33%

Feed Grade Copper (%)

0.43

0.50

-13%

84%

89%

-6%

Recovery Silver (%)

85%

88%

-4%

74%

69%

7%

Recovery Gold (%)

74%

70%

6%

81%

88%

-8%

Recovery Copper (%)

84%

87%

-4%

263,231

281,831

-7%

Total Silver Produced (oz)

812,530

825,420

-2%

1,935

1,625

19%

Total Gold Produced (oz)

5,933

4,917

21%

1,307,429

1,771,250

-26%

Total Copper Produced (lbs)

4,372,752

4,423,909

-1%

580,780

670,887

-13%

Total Silver Equivalent Produced (oz) 1

1,904,840

1,916,940

-1%

"This quarter's results reflect the natural variability in our mining sequence, but our overall performance remains solid, and we're on track to meet our annual production guidance range," said David Wolfin, President and CEO of Avino. "We have continued to focus on operational excellence, and it's demonstrated in our high mill availability and sustained throughput. The progress at La Preciosa has been exceptional. We are excited to start transporting stockpiled material from La Preciosa to the mill at Avino, well ahead of expectations, as we move closer to announcing first production. In addition, the incredible rise in metal prices has provided a welcome boost to our margins, supporting our continued growth."

Balance Sheet Update

Avino had approximately US$55 million in cash at September 30th, 2025. Our balance sheet continues to strengthen as we execute on our transformational growth strategy.

La Preciosa Update

The Gloria and Abundancia veins have been intercepted on the San Fernando ramp that has been driven from surface. The ramp continues to be driven, with progress currently down to Level 4. Over 6,700 tons of mineralized material had been stockpiled as of the end of Q3 2025, and trucking to the Avino Mill for processing is now underway. Hiring and training of equipment operators is ongoing and currently employs seventy people working across three shifts. All requirement mining equipment is on site already and standby equipment has been purchased to ensure continuous operation of site services. Offices and other building infrastructure are also being added. Recent photos showcasing the work at La Preciosa are available on the Avino website - click here to view them.

Exploration Program and Resource & Reserve Update

At Avino, the ramp at the Elena Tolosa ("ET") area has been driven down to Level 17.5, as we continue with development for future production mining. The 2025 drilling program commenced in April with a program consisting of nine planned holes from surface, with six now complete. The objective of the ET Area drill program is two-fold; One to test the downdip extension of the system below the current lowest mining level, following the trend of previous drilling reported on September 14, 2023 as well as to test the extension of the system along strike to the west. The Avino Vein remains open at depth and along strike, and earlier results have shown comparable grades and widths to those currently being mined. Drilling continues with over 3500m drilled to date. The latest results will be publicized when the assays have been received, and all data has been verified.

A second surface drill was deployed at La Preciosa to confirm prior drill results from previous operators and to improve the understanding of the grade zonation close to the scheduled mining areas near the ramp. Earlier drill core from previous operators, was extensively utilized to provide sample data for earlier technical reports, so remaining samples were limited. Since the last drill results were release ( August 18, 2025 ) drilling has continued and the latest results will be publicized when all the assays have been receive and all data has been verified. Drilling information will be utilized in underground mine planning, 3D modelling as well as an update to the Resource estimate that is due in Q1 2026. In addition, Avino is planning on releasing its first mineral reserve estimate at the same time as the Company has now met the requirements for a Producing Issuer under the NI 43-101 standards of disclosure for mineral projects.

Earnings Announcement

The Company's unaudited condensed consolidated interim financial statements for the Third Quarter 2025, will be released after the market closes on Thursday, November 6, 2025.

A conference call to discuss the Company's Q3 2025 operational and financial results will be held on Friday, November 7, 2025, at 8:00 a.m. PT / 11:00 a.m. ET. To participate in the conference call or follow the webcast, please see the details below.

Shareholders, analysts, investors, and media are invited to join the webcast and conference call by logging in here Avino's Q3 2025 Financial Results or by dialing the following numbers five to ten minutes prior to the start time.

  • Toll Free: 888-506-0062

  • International: +1 973-528-0011

  • Participant Access Code: 530885

Participants will be greeted by an operator and asked for the access code. If a caller does not have the code, they can reference the Company name. Participants will have the opportunity to ask questions during the Q&A portion.

The conference call and webcast will be recorded, and the replay will be available on the Company's website later that day.

Quality Assurance/Quality Control

Mill assays are performed at the Avino property's on-site lab. Check samples were submitted to SGS Labs in Durango, Mexico for verification. Gold and silver assays are performed by the fire assay method with a gravimetric finish for concentrates and AAS (Atomic Absorption Spectrometry) methods for copper, lead, zinc and silver for feed and tail grade samples. All concentrate shipments are assayed by one of the following independent third-party labs: Inspectorate in the UK, LSI in the Netherlands, and AHK.

Qualified Person(s)

Peter Latta, P.Eng., MBA, Avino's VP Technical Services, is a qualified person within the context of National Instrument 43-101, has reviewed and approved the technical data in this news release.

About Avino

Avino is a silver producer from its wholly owned Avino Mine near Durango, Mexico. The Company's silver, gold and copper production remains unhedged. The Company intends to maintain long term sustainable and profitable mining operations to reward shareholders and the community alike through our growth at the historic Avino Property and the strategic acquisition of the adjacent La Preciosa which was finalized in Q1 2022. Early in 2024, the pre-feasibility Study on the Oxide Tailings Project was completed. This study is a key milestone in our growth trajectory. As part of Avino's commitment to adopting sustainable practices, we have been operating a dry-stack tailings facility for more than two years now with excellent results. We are committed to managing all business activities in a safe, environmentally responsible, and cost-effective manner, while contributing to the well-being of the communities in which we operate. We encourage you to connect with us on X (formerly Twitter) at @Avino_ASM and on LinkedIn at Avino Silver & Gold Mines . To view the Avino Mine VRIFY tour, please click here .

For Further Information, Please Contact:

Investor Relations
Tel: 604-682-3701
Email: IR@avino.com

This news release contains "forward-looking information" and "forward-looking statements" (together, the "forward looking statements") within the meaning of applicable securities laws and the United States Private Securities Litigation Reform Act of 1995, including the mineral resource estimate for the Company's Avino properties, including La Preciosa, located near Durango in west-central Mexico (the "Avino Property") with an effective date of October 16, 2023, and can be viewed within Avino's latest technical report dated February 5, 2024 for the Pre-feasibility Study and references to Measured, Indicated Resources, and Proven and Probable Mineral Reserves referred to in this press release. This information and these statements, referred to herein as "forward-looking statements" are made as of the date of this document. Forward-looking statements relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: (i) the estimated amount and grade of mineral reserves and mineral resources, including the cut-off grade; (ii) estimates of the capital costs of constructing mine facilities and bringing a mine into production, of operating the mine, of sustaining capital, of strip ratios and the duration of financing payback periods; (iii) the estimated amount of future production, both ore processed and metal recovered and recovery rates; (iv) estimates of operating costs, life of mine costs, net cash flow, net present value (NPV) and economic returns from an operating mine; and (v) the completion of the full Technical Report, including a Preliminary Economic Assessment, and its timing. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "envisages", "assumes", "intends", "strategy", "goals", "objectives" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements. These forward-looking statements are made as of the date of this news release and the dates of technical reports, as applicable. Readers are cautioned not to place undue reliance on forward-looking statements, as there can be no assurance that the future circumstances, outcomes or results anticipated in or implied by such forward-looking statements will occur or that plans, intentions or expectations upon which the forward-looking statements are based will occur. While we have based these forward-looking statements on our expectations about future events at the date that such statements were prepared, the statements are not a guarantee that such future events will occur and are subject to risks, uncertainties, assumptions and other factors which could cause events or outcomes to differ materially from those expressed or implied by such forward-looking statements.

Cautionary note to U.S. Investors concerning estimates of Mineral Reserves and Mineral Resources

All reserve and resource estimates reported by Avino were estimated in accordance with the Canadian National Instrument 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Definition Standards. The U.S. Securities and Exchange Commission ("SEC") now recognizes estimates of "measured mineral resources," "indicated mineral resources" and "inferred mineral resources" and uses new definitions of "proven mineral reserves" and "probable mineral reserves" that are substantially similar to the corresponding CIM Definition Standards. However, the CIM Definition Standards differ from the requirements applicable to US domestic issuers. US investors are cautioned not to assume that any "measured mineral resources," "indicated mineral resources," "inferred mineral resources", "proven mineral reserves", or "probable mineral reserves" that the Issuer reports are or will be economically or legally mineable. Further, "inferred mineral resources" are that part of a mineral resource for which quantity and grade are estimated on the basis of limited geologic evidence and sampling. Mineral resources which are not mineral reserves do not have demonstrated economic viability.

Neither TSX nor its Regulation Services Provider (as that term is defined in the policies of the TSX) accepts responsibility for the adequacy or accuracy of this release.

Footnotes:

  1. In Q3 2025, AgEq was calculated using metal prices of $39.38 per oz Ag, $3,454 per oz Au and $4.45 per lb Cu. In Q3 2024, AgEq was calculated using $29.42 per oz Ag, $2,476 per oz Au and $4.18 per lb Cu. For YTD 2025, AgEq was calculated using metal prices of $34.98 per oz Ag, $3,199 per oz Au and $4.34 per lb Cu. For YTD 2024, AgEq was calculated using metal prices of $28.24 per oz Ag, $2,387 per oz Au and $4.15 per lb Cu. Calculated figures may not add up due to rounding.

SOURCE: Avino Silver & Gold Mines Ltd.



View the original press release on ACCESS Newswire

Investment Disclosure



The content provided on this website and in Mine$tockers episodes is for informational purposes only and should not be considered as an offer, solicitation, recommendation, or determination by Mine$tockers Inc. for the sale of any financial product or service or the suitability of an investment strategy for any investor.

Investors are advised to consult a financial professional to determine the appropriateness of an investment strategy based on their objectives, financial situation, investment horizon, and individual needs. This information is not intended to serve as financial, tax, legal, accounting, or other professional advice, as such advice should always be tailored to individual circumstances.

The products discussed herein are not insured by any government agency and carry risks, including the potential loss of the principal amount invested. Any information provided is based on both internal and external sources and should not be construed as an endorsement or conclusion regarding a company's financial prospects, resources, or management. Opinions expressed may change and should not be relied upon. It is crucial to seek personalized investment advice for your unique situation.

Natural resources investments are generally volatile, with higher headline risk than other sectors. They tend to be more sensitive to economic data, political and regulatory events, and underlying commodity prices. The prices of natural resources investments are influenced by factors such as the costs of underlying commodities like oil, gas, metals, and coal. These investments may trade on various exchanges and experience price fluctuations due to short-term demand, supply, and investment flows.

Natural resource investments often respond more sensitively to global events and economic data, including natural disasters, political turmoil, pandemics, or the release of employment data.

Investing in foreign markets may carry greater risks than domestic markets, including political, currency, economic, and market risks. It is essential to evaluate if trading in low-priced and international securities is appropriate for your circumstances and financial resources. Past performance does not guarantee future results.

Mine$tockers Inc., its affiliates, family, friends, employees, associates, and others may hold positions in the securities it covers. Some of the companies covered may be paying clients of the production.

No investment process is risk-free, and profitability is not guaranteed; investors may lose their entire investment. No investment strategy or risk management technique can guarantee returns or eliminate risk in any market environment. Diversification does not ensure a profit or protect against loss. Investing in foreign securities involves risks not associated with domestic investments, such as currency fluctuations, political and economic instability, and differing accounting standards, potentially leading to greater share price volatility. The prices of small- and mid-cap company stocks generally experience higher volatility than large-company stocks and may involve higher risks. Smaller companies may lack the management expertise, financial resources, product diversification, and competitive strengths needed to withstand adverse economic conditions.

logo

Studio


Toronto Ontario Canada

Email


kevin@MineStockers.com

Phone


+1 (905) 967-2519